What is holding the noida metro back?

feature-image

Play all audios:

Loading...

The Aqua Line Metro has been touted as the lifeline of Greater Noida residents, including those living on the outskirts of Noida. But the metro line hasn’t been made available to the public


yet. The line will connect some areas of Greater Noida to the Delhi Metro, improving access to Delhi and Gurugram for Noida residents. The metro has received all clearances, fares have been


announced, even smart cards are being produced in partnership with State Bank of India. It is safe to say that the Noida metro line is ready for launch, PD Upadhyay, executive director of 


Noida Metro Rail Corporation, told _The Indian Express_. He added: “We have sent the proposal to the government seeking a launch date. From our end, all due diligence is complete. We have


been given a go-ahead by the safety commissioner as well.” So what is stopping the Noida metro line from going public? The Aqua Line is awaiting a formal inauguration. It is being speculated


that the Prime Minister’s Office is yet to provide an available date. The BJP wants to inaugurate the line as close to the elections as possible, some claim. Others reasons for delay may


include the authorities wanting to wait for the extension of the Blue Line. Nevertheless, the NMRC has neither cleared up any of these speculations nor offered a fixed timeline. THE LACK OF


ACHHE DIN FOR NMRC The Aqua Line, expected to be functional in April 2018, was first delayed in 2017, after lack of funds delayed the pick up of its made-in-China coaches from Mumbai. The


three-month delay in commencement of its major power supply source—a substation in Sector 148, Noida, further delayed its launch. A victim of departmental and administrative delays, the line


costing over Rs 5,500 crore was then targeted to be completed in December 2018—the line had already missed two deadlines in April and October. Finally, it was cleared for operations after


three trials and approval from the Commissioner of Metro Rail Safety. However, December being the month of Kharmas, an inauspicious period in which people do not initiate any new tasks, the


project was delayed further. “We were earlier aiming for Christmas 2018 but could not get a date then. We then entered Kharmas and it is unlikely that it [the launch] happens during this


period. We’re hoping it’s done after Makar Sankranti with the opening of the new Kalindi Kunj Bridge this month,” a senior Metro official said. A six-lane bridge across the Yamuna river,


near Kalindi Kunj, is also waiting for a final heads up. Speaking about the delay, local activist Abhisht Gupta told _Newslaundry_, “It is a troublesome situation for us. There’s conjecture


that PM Modi’s availability for the inauguration was under doubt and since then it keeps getting delayed. I see the metro running all day, all empty; a lot of public money has been invested


in the project. If we can’t use it in need, it is a waste of public money.” Any further delay will only add to make to NMRC’s challenges. For example, the metro which is currently running


empty under trial can accommodate up to 1,034 riders. The fare for the journey from the first station to the last station is Rs 50. This is to say that the NMRC is losing out on about Rs


51,700 per run. Additionally, if the inauguration doesn’t take place by January 31, NMRC will have to reapply for a CMRS clearance, which would need more trials and thus, further delay Aqua


Line’s launch. UPDATE: _News18_ has reported the Aqua Line Metro is likely to be inaugurated on January 25 by Uttar Pradesh Chief Minister Yogi Adityanath.