• Installation of fuel tanks on the west side of the medical facility continues.  • Utility work continues in the south portion of the site.  • Work on the loading dock and laundry on the


west side of the medical facility will begin soon.  • Work on a water tower foundation will begin in the next few weeks on the north side of the site.  • Construction of the South Parking


Structure continues with placement of pre-cast panels being installed.  • Work continues on placing the roof portion of the sanitary tank in the southwest corner of the property.  • Exterior


metal wall framing continues on the west and south side of the West Bar of the medical facility.  • Interior framing and utility rough in is taking place in the West Bar of the medical


facility.  • Decking and concrete placement in the East Bar of the medical facility is ongoing.  • Utility installation continues to be installed in the North Parking Structure.  • Central


Utility Plant continues to have utilities and equipment installation ongoing.  • Work continues on both the Eastern Electrical Building near the USACE trailer and the Western Electrical


Building just north of the North Parking Structure.  • The installation of underground utilities continues across the site.  ADDITIONAL NOTES: If you have specific questions about the


construction of the new medical center, please send us an email at [email protected]. For the most recent information on the project, please visit