[withdrawn] planned roadworks in yorkshire and the humber – summary for monday 10 august to sunday 16 august

feature-image

Play all audios:

Loading...

Press release PLANNED ROADWORKS IN YORKSHIRE AND THE HUMBER – SUMMARY FOR MONDAY 10 AUGUST TO SUNDAY 16 AUGUST Planned new and ongoing road improvements over the coming week. THIS NEWS


ARTICLE WAS WITHDRAWN ON 16 JUNE 2017 These bulletins are now sent directly to journalists. Contact the Highways England Press Office directly to be added to the circulation list. Otherwise


you can check on the live roadworks search tool. The following summary of planned new and ongoing road improvements over the coming week is correct as of Friday 7 August and could be subject


to change due to weather conditions or unforeseen circumstances. All our improvement work is carried out with the aim of causing as little disruption as possible. M1 JUNCTION 30


CHESTERFIELD TO JUNCTION 31 WORKSOP There are currently narrow lanes and a 50mph speed limit in both directions as part of the smart motorway scheme. The hard shoulder is also closed, and


the project is due to be completed in the autumn. The southbound exit slip road at junction 31 will be closed for 2 nights from 13 August. The northbound entry slip road at junction 31 will


be closed for five nights from 11 August. The northbound exit slip road at junction 31 will be closed overnight on 15 August. The northbound and southbound side of the motorway will be


reduced to a single lane for 5 nights from Monday 10 August. The closures will take place between 8pm and 6am, and drivers will be able to follow clearly-signed diversion routes. M1 JUNCTION


34 TINSLEY TO JUNCTION 35A STOCKSBRIDGE The hard shoulder is currently closed in both directions as part of the smart motorway scheme. There will be narrow lanes and a 50mph speed limit


until the project is completed in winter 2016. M1 JUNCTION 36 TANKERSLEY The southbound exit slip road will be closed for two nights for resurfacing works from Wednesday 12 August. The


closures will take place between 8pm and 6am, and drivers will be able to follow clearly signed diversion routes. M1 JUNCTION 38 HAIGH The northbound exit slip road will be closed for 2


nights for resurfacing works from Monday 10 August. The closures will take place between 8pm and 6am, and drivers will be able to follow clearly signed diversion routes. M1 JUNCTION 39 DENBY


DALE TO JUNCTION 42 (M62 INTERCHANGE) The hard shoulder is currently closed in both directions as part of the smart motorway scheme. There will be narrow lanes and a 50mph speed limit in


place until the project is completed in autumn 2015. The northbound entry slip road at junction 39 and the northbound entry slip road at junction 41 will be closed overnight on Monday 10


August. The southbound entry slip road at junction 41 and the southbound exit slip road at junction 39 will be closed overnight on Tuesday 11 August. The southbound entry slip road at


junction 41, the southbound exit at junction 40 and the southbound exit slip road at junction 39 will be closed overnight on Wednesday 12 August. The southbound exit slip road at junction 41


and the northbound entry slip road at junction 41 will be closed overnight on Thursday 13 August. The northbound and southbound side of the motorway will be reduced to a single lane for 5


nights from Monday 10 August. The closures will take place between 8pm and 6am, and drivers will be able to follow clearly signed diversion routes. M18 JUNCTION 3 DONCASTER TO JUNCTION 4


DONCASTER The northbound side of the motorway between junctions 3 and 4 will be closed overnight for 2 nights for resurfacing works from Friday 14 August. The closures will take place


between 8pm and 6am, and clearly signed diversions will be in place. M18 JUNCTION 3 DONCASTER The northbound exit slip road will be closed for five nights from Monday 10 to 13 August and 16


August. The closures will take place between 8pm and 6am, and drivers will be able to follow clearly signed diversion routes. M62 JUNCTION 26 BRADFORD (M606 INTERCHANGE) There will be narrow


lanes and a 30mph speed limit in place until the project is completed in April 2016. The slip roads and roundabout at the junction will be reduced to a single lane overnight for 5 nights,


between 7pm and 6am, from Monday 10 August. M62 JUNCTION 26 BRADFORD (M606 INTERCHANGE) The eastbound entry slip road and 2 plus lane will be closed overnight on Sunday 16 August, the


closure will take place between 8pm and 6am. There will be clearly signed diversion route. M62 JUNCTION 29 LOFTHOUSE (M1/M62 INTERCHANGE) The westbound exit slip road will be closed


overnight on Thursday 13 August, the closure will take place between 8pm and 6am. There will be clearly signed diversion route. M606 JUNCTION 3 STAYGATE The southbound entry slip road will


be closed for 5 nights for barrier renewal works from Monday 10 August. The closures will take place between 8pm and 6am, and drivers will be able to follow clearly signed diversion routes.


M606 JUNCTION 2 EUROWAY TO JUNCTION 3 STAYGATE The northbound side of the motorway will be reduced to a single lane overnight for 5 nights for carriageway improvement works from Monday 10


August, between 8pm and 6am. M621 JUNCTION 4 HUNSLET The clockwise exit slip road will be closed for routine maintenance works on Saturday 15 August. The closures will take place between 5am


and 10am, and drivers will be able to follow clearly signed diversion routes. M621 JUNCTION 4 HUNSLET The anticlockwise exit slip road will be closed for routine maintenance works on Sunday


16 August. The closures will take place between 5am and 10am, and drivers will be able to follow clearly signed diversion routes. A180/A160 IMMINGHAM, HUMBERSIDE There will be narrow lanes


on the A180 and A160 along with a 50mph speed limit while work takes place to improve access to the Port of Immingham, including upgrading the A160 to a dual carriageway. The project is due


to be completed in autumn 2016. The westbound exit slip road at Brocklesby will be closed until August 2016 and the eastbound entry slip road at Brocklesby will be closed until August 2016.


A616 WORTLEY, SOUTH YORKSHIRE The westbound side of the trunk road will be closed overnight for carriageway improvement works on Monday 10 August. The closures will take place between 8pm


and 6am, and drivers will be able to follow clearly signed diversion routes. A616 MIDHOPESTONES, SOUTH YORKSHIRE There will be convoy works eastbound and westbound for carriageway


improvement works for 4 nights from Tuesday 11 August between 8pm and 6am. A64 COPMANTHORPE TO ASKHAM BRYAN, YORK The westbound side of the trunk road will be closed overnight for 4 nights


for carriageway improvement works from Monday 10 August. The closures will take place between 8pm and 6am, and drivers will be able to follow clearly signed diversion routes. GENERAL


ENQUIRIES Members of the public should contact the Highways England customer contact centre on 0300 123 5000. MEDIA ENQUIRIES Journalists should contact the Highways England press office on


0844 693 1448 and use the menu to speak to the most appropriate press officer. SHARE THIS PAGE The following links open in a new tab * Share on Facebook (opens in new tab) * Share on Twitter


(opens in new tab) UPDATES TO THIS PAGE Published 7 August 2015